Project Specification: Concrete bridge deck has three decks. Each deck also has 12 piles. Each deck width of 17 meters and length of the deck 20 meters is. And the above deck are a 2% slope. (Central 2% slope to the sides and deck side with 2% slope to the center circle are.)
Each of the parties retaining walls bridge piles with a diameter of 136 m and a height of 9 to 15 meters is on the column height of 3 to 6 meters are running.
Axis to axis distance first to the last pile is 405 meters with a wall thickness of 20 cm in length and covered the entire wall is 547 meters.
 
Location:                 Ivory Coast – Rivera
Client:                      Ministry of Construction and Economy of Ivory Coast
Contractors:          Ariane Infrastructure Development Company
Type of Contract:    EPC
Contract duration:  14 Month
Project Status:  Ongoing
 